Tuesday, January 18, 2011

KDN Kangar 18 Januari 2011


Gambar-gambar sekitar KDN Kangar pada 18 Januari 2011, ad aantaranya gambar defect so jangan dibuat contoh.

Ambil yang baik-baik sahaja.

Progress sekitar 40% M&E, perakuan pembayaran 25%.

Sekian terima kasih.

Ir. MUHAMMAD ARKAM
www.arkamonline.com

Thursday, November 11, 2010

Monday, March 29, 2010

KHEDN Kangar 29 Mac 2010

Mesyuarat Tapak KHEDN kali ke 11: Laporan seperti berikut:

Kemajuan Kerja Fizikal

Schedule=13%
Actual=23%
Ahead 10%.



Ir. MUHAMMAD ARKAM
www.arkamonline.com

Saturday, March 13, 2010

KHEDN Kangar 11th March 2010

Site progress as of 11th March 2010:

Ground floor concrete slab: 100%
1st floor concrete slab: 75%
Proceed to 2nd floor slab and beam formwork at Zone A.

M&E follows accordingly.



Ir. MUHAMMAD ARKAM
www.arkamonline.com

Sunday, January 31, 2010

Laporan M&E KHEDN Kangar Januari 2010

Laporan M&E KHEDN Kangar boleh di download daripada ikon di bawah:



Gambar-gambar progress boleh diperolehi daripada blog ini dengan klik pada label KHEDN Kangar.

Sekian, terima kasih...

Ir. MUHAMMAD ARKAM
www.arkamonline.com

Thursday, January 14, 2010

KHEDN Kangar 14 Januari 2010

Bermula pagi jam 900 Mesyuarat Perunding, 1100 Mesyuarat Teknikal, 230 ptg Mesyuarat Koordinasi... Gambar terbaru seperti berikut:



Terima kasih...

Ir. MUHAMMAD ARKAM
www.arkamonline.com